Do you ever notice how sometimes the little ignorance
could invite biggest problems?
This situation can be compounded when a variable is
considered insignificant and accordingly ignored. Such can be the case when
tack welds are improperly made.
Code books define a tack weld as: “A weld made to hold
the parts of a weldment in proper alignment until the final welds are made.”
While the term “temporary weld” is defined as: “A weld
made to attach a piece to a weldment for temporary use during handling,
shipping, or working on the weldment.”
The clear difference is that the tack weld joins “the
parts of a weldment,” where as the temporary weld joins “another piece
of metal to a weldment” like Bridge, Fit up Clamps, Jigs & Fixtures.
Keep definitions aside & ensure both tack welds and
temporary welds must be properly made. Since there is no secondary member term
in welded construction. Improperly made tack or temporary welds may create
problems that result in the propagation of cracks into main members.
Further, temporary welds may provide metallurgical path
for cracks (if present) in attachments to propagate through the weld, into the
main member. Even though these welds seem to be less important but would be
critical, especially in weldments subject to cyclic loading.
Unfortunately tack welds
are usually given little attention.
Consider the improper procedure were followed while
making a tack weld outside the joint, the weld is made without preheat or required
minimum heat input or correct electrode. Such practice could result in
development of under bead cracks, an excessive hard HAZ or other weld defects.
Simple removal of tack weld metal from the surface of the steel will not
automatically remove the defect that may reside in the base metal. This can
result in performance problems for the weldment, particularly when subject to
cyclic loading.
Very hard, brittle, crack sensitive micro structures,
such as Martensite and upper Bainite were formed in many metals when rapidly
quenched from an elevated temperature. The brittle micro structure is likely to
crack during solidification of the weld metal or when highly stressed during
operation. The cracks are usually an under bead cracks & difficult to
detect by NDE (Visual or DPT/ MPT/ RT). Yet these small cracks may lead to the
product failure in near future due to cyclic fatigue of the cylindrical
equipment.
How does this apply to
tack welds?
During fabrication of cylindrical
components a high heat input process is selected for the welding but the tack
weld is made by SMAW process. The tack weld is a very rapid quench application
resulted in a brittle, crack sensitive micro structure at the root of the weld.
The tack may be subsequently pulled and stressed during the fit up operation
with a resultant under bead crack at the root of the weld. The crack may
propagate further into the base metal during the subsequent welding operations.
During fit- up of process piping, normally weldments are
held in position by tacking in the grove joint. Tack welds are often made with
a different welding process, or same process with different filler metal other
than for final weld. In such a case chemical interactions between these two
types of filler materials should be consider (more important in case of cladded
pipes)
A second type of interaction that must be considered is
the potential effect of intermixed weld metals on mechanical properties. The
toughness of subsequent weld passes of normally tough welds may be reduced due
to negative interaction with tack welds made with a different shielding system
/ filler material during welding.
That’s why ASME
BPVC requires Tack weld or Temporary welds shall be subject to the same WPS requirements
as the final welds.
Poorly applied tack welds are frequently the cause of entrapped
slag, porosity, lack of penetration, and cracks. Even a small tack weld on
non-preheated thicker sections may result in a hard, crack sensitive heat
affected zone around the tack weld.
There are many preventive measures to counter this
problem such as preheat, high heat input processes, subsequent Post Weld Heat
Treatment etc.
If the vessel is to be Post Weld
Heat Treated then the WPS for the tack welding shall be qualified with PWHT. If
the welding process is qualified with preheat, the tack weld shall be applied
within the preheat range qualified.
ASME BPVC Section I, VIII & B 31.3 requires that tack
welding procedure to be qualified in accordance with the referencing code
section i.e. ASME Section IX.
Tack welds made at the root of a groove weld must be
qualified by a groove weld test in accordance with the requirements of Section
IX. Tack welds of the fillet type may be qualified by a groove weld test or
fillet weld test in full compliance with the requirements of Section IX.
There is at least one exception to this, Section VIII (UW-28)
& Section I (PW-28) state that, procedure qualification is not required for
any machine welding process used for attaching non pressure bearing attachments
to pressure parts which have essentially no load carrying function.
The performance
qualification of welders for tack welding is also largely ignored and
uncontrolled.
Performance qualification
of tack welders is required as recommended in UW-31 of Section VIII, PW-31 of
Section I & 328.5 of B 31.3 when the tack weld is
left in place or is incorporated into the weld.
As per ASME section – I & VIII Performance
qualification is not required if the tack weld is going to remove while it is
not the case for Bridge tack weld as per clause 328.5.1(c) of ASME B 31.3.
Essential variables to include during performance qualification of welders for tack welding are backing, base metal type, position, deposited weld metal thickness range.
Tack welds may be placed
within the weld joint, and then subsequently welded over with the other weld
passes. Alternately, tack welds may be made outside the weld joint too.
For tack welds made within the weld joint, may be
completely remelted and becomes part of the final weld.Tack welds made outside
the joint may remain in place, and become part of the permanent weldment, or
they may be removed after the joint has been partially or completely welded.
When tack welds or temporary welds are required to be
removed, it is important that the weld metal shall be fully removed without
damaging the base metal. A typical approach is to thermally cut the weld
or attachment off (using air arc gouging, oxy fuel cutting) away from base
metal, and follow up with grinding & NDT.
When cutting is performed too close to the final surface,
one may inadvertently gouge the base metal.
Some important facts to be consider on tack welds:
- Removal of a tack weld
means removal of the deposited weld metal essentially flush with the parent
base metal.
- Tack welds leaves the heat affected zone and some weld / base
metal mixture which may contain brittle, crack sensitive structure. Removal may
also be complete, as in the case of back gouging to sound metal.
- Tacks shall be visually
examined for defects and, if discovered, the defects shall be removed. Normally
the defects are entrapped slag, gas pockets, lack of fusion, cracks, etc.
- Tacks are often pulled
and stressed, cracking or tearing away base metal. These defects must be
removed before making the final weld.
- Tack welds may be long
or short. During site fabrication of process piping some fit up many welders /
fitters making tacks more than half the length of the root. This is why a
welder who is performing tack welding activity in the root of a single welded
butt joint needs to be qualified for welding without backing.
ASME Section I
- PW-28.4.3 Identification of
welders or welding operators making tack welds that become part of a final
pressure retaining weld or structural attachment weld is not required provided
the Quality Control System of the Manufacturer includes a procedure to permit
the Inspector to verify that such tack welds were made by qualified welders or
welding operators.
- PW-31.3 Tack welds used to
secure alignment shall either be removed completely when they have served their
purpose or their stopping and starting ends shall be properly prepared by
grinding or other suitable means so that they may be satisfactorily
incorporated into the final weld.
- Tack welds, whether
removed or left in place, shall be made using a fillet weld or butt weld
procedure qualified in accordance with Section IX.
- Tack welds to be left in
place shall be made by welders qualified in accordance with Section IX and
shall be examined visually for defects and, if found to be defective, shall be
removed.
ASME Section VIII
- UW-31(c) Bars, jacks, clamps,
tack welds, or other appropriate means may be used to hold the edges of parts
in alignment.
- Tack welds used to
secure alignment shall either be removed completely when they have served their
purpose, or their stopping and starting ends shall be properly prepared by
grinding or other suitable means so that they may be satisfactorily
incorporated into the final weld.
- Tack welds, whether
removed or left in place, shall be made using a fillet weld or butt weld
procedure qualified in accordance with Section IX.
- Tack welds to be left in
place shall be made by welders qualified in accordance with Section IX, and
shall be examined visually for defects, and if found to be defective shall be
removed.
- UHT-85 (a & c) Structural
& Temporary Welds -Welds for pads, lifting
lugs and other non pressure parts, as well as temporary lugs for alignment,
shall be made by qualified welders in full compliance with a qualified welding
procedure.
- Temporary welds shall be
removed and the metal surface shall be restored to a smooth contour. The area shall
be inspected by magnetic particle or liquid penetrant method for the detection
and elimination of cracks. Temporary welds shall be considered the same as all
other welds so far as requirements for qualified operators and procedures and
for heat treatment are concerned.
ASME B 31.3, 328.5.1(c)
- Tack welds shall be made
by a qualified welder or welding operator.
- Tack welds at the root
of the joint shall be made with filler metal equivalent to that used in the
root pass.
- Tack welds shall be
fused with the root pass weld. Bridge tacks (above the weld) shall be removed.
Summary
Neither tack welds nor temporary welds should be viewed
as unimportant, secondary welds, particularly when applied to cyclically loaded
weldments. Whether the tack weld is to be made in the joint or not will affect
the overall approach to the weld.
For tack welds and temporary welds that will be removed,
care must be taken to protect the base metal. There are plenty of opportunities
to make tack and temporary welds improperly. Fortunately, it is not difficult
to make them correctly.
Next time when you meet
a tack weld, face it with respect. Qualify the tack weld procedure, qualify the
tack welder’s performance and control the application of the tack in accordance
with your quality control program. A respected tack weld may pay you back with
dividends of which you may never have been aware. The dividends may be no x-ray
repairs, no leaks and no product failure.
TENS Unit Electrode 2x2 40 Pcs Replacement Electrode Pads for all Electrotherapy Tens machine.
ReplyDeleteQantice: Tack Welds Or Temporary Welds: Unfortunately Most Disregarded Variable In Fabrication Industry. >>>>> Download Now
Delete>>>>> Download Full
Qantice: Tack Welds Or Temporary Welds: Unfortunately Most Disregarded Variable In Fabrication Industry. >>>>> Download LINK
>>>>> Download Now
Qantice: Tack Welds Or Temporary Welds: Unfortunately Most Disregarded Variable In Fabrication Industry. >>>>> Download Full
>>>>> Download LINK kx
Thanks for this post… Welder Qualification Test is Welder should perform the test weld on the similar coupon following all the variables given the approved WPS. Example (position, approved filler metal, approved base metal, allowed Electrical characteristics, allowed Gas flow rate, Pre heat & post weld heating requirements. Perform Visual and NDT tests, Macro tests on the weld coupon and qualify the welder. Welder qualification certificate should be renewed 6 months once, as per code requirement.
ReplyDeleteWater bag rental in Saudi
Eddy Current Testing
Tank Calibration Services
Qantice: Tack Welds Or Temporary Welds: Unfortunately Most Disregarded Variable In Fabrication Industry. >>>>> Download Now
ReplyDelete>>>>> Download Full
Qantice: Tack Welds Or Temporary Welds: Unfortunately Most Disregarded Variable In Fabrication Industry. >>>>> Download LINK
>>>>> Download Now
Qantice: Tack Welds Or Temporary Welds: Unfortunately Most Disregarded Variable In Fabrication Industry. >>>>> Download Full
>>>>> Download LINK