Recently on my previous project I face MIC phenonena on SS 316L CIP Tank.Pits observed on 6 mm thick. tank base, Man Hole & on Shell up to stangent water level. Tank found leaking post 2 months of commissioning. See below snaps,
Microbiologically-Influenced Corrosion (MIC), also known as microbial corrosion or biological corrosion, is the deterioration of metals as a result of the metabolic activity of microorganisms.
There are about a dozen of bacteria known to cause microbiologically influenced corrosion of carbon steels, stainless steels, aluminum alloys and copper alloys in waters and soils with pH 4~9 and temperature 10oC~50oC.
These bacteria can be broadly classified as aerobic (requires oxygen to become active) or anaerobic (oxygen is toxic to the bacteria). Sulphate reducing bacteria (SRB) is anaerobic and is responsible for most instances of accelerated corrosion damages to ships and offshore steel structures. Iron and manganese oxidizing bacteria are aerobic and are frequently associated with accelerated pitting attacks on stainless steels at welds.
Industries hardest hit with high cost of repairs and
replacements, plus lost revenues due to process
downtime, are Onshore and offshore oil and gas industry, chemical process and nuclear power
generation.
Pinhole leaks due to Microbiologically
Influenced Corrosion (MIC) of 300 series stainless steel piping system have
often occurred even before plant start- up; there are many cases of such
failures in the industry. The problem is typically caused by residual water
left in the system for extended period of time following hydro testing,
flushing or commissioning during construction or extended shut downs. When such
water is remain for a prolonged period, microbial activity can create an
environment in which rapid chloride pitting corrosion occurs at much lower
chloride concentrations then would normally be considered possible for the
affected grade of stainless steel (e.g. 304,316 or 321) at ambient temperature.
Although this topic has been widely discussed in oil & gas industry still
there is general lack of awareness among the wider engineering disciplines.
Consequently, it is the intent of this blog to heightened awareness &
understanding of this problem & thereby assists to reduce the probability
of this type of failure occurring in the future.
Background
MIC Failures caused by stagnant water -
MIC commonly results when residual water is left in stainless steel system
after hydro static testing or similar activities, and perforation of 3 mm thick
piping in such circumstances has occurred in as little as 1 month.
Some examples are summarized below,
Some examples are summarized below,
Case #1- Potable Well Water for Hydro
test
The failure of 304 SS piping that was
hydro tested with potable well water containing about 250 ppm chloride. During
hydro testing, the water was continuously chlorinated to prevent MIC, but the
lines were not completely drained after testing & sat idle for 5 months.
Within 24 hours of being placed in service, leaks were observed &
radiography confirms that 80 % of welds contained extensive subsurface pitting
damage. A powdery reddish brown deposit was found on internal pipe surface
& failure mechanism was diagnosed as MIC.
Case #2- Samples from Different Power
Plant, USA
The examination of twelve pipe sections
of 304, 304L SS from different power plants in USA. The sections were each from
horizontal pipes in which hydro test water had been left stagnant for several
months before the plant was put in to service. For the 11 samples that had
suffered from pitting corrosion, the common characteristics included pitting in
the bottom third of the pipe, pits predominantly at or adjacent to welds,
reddish mounds of deposits above each pit & extensive sub surface damage
beneath pinholes visible at the surface.
Mechanism of MIC in SS in Natural
Waters
The case studies above show that Iron
Oxidising Bacteria (IOB), Manganese Oxidisng Bacteria (MnOB) & Sulphate
Reducing Bacteria (SRB) are each often implicated in the MIC of SS caused by
stagnant waters (such as residual hydro test water).
Stagnant & low flow conditions
promote attachment of bacteria to metal surface. Attachment is followed by
colonization & formation of discrete deposits, starting as a film (bio
film) & frequently developing as bulky deposits (biomound). Composition of
deposits is significantly different & more corrosive then the bulky water
environment. Thus under deposit corrosion occurs by formation of concentration
cells. And corrosion is accelerated because the oxygen that is essential to the
stability of passive film is prevented from diffusing to the occluded sites.
Conclusion –
The occurrence of pinhole leaks due to
microbiologically Influence corrosion (MIC) in ASS (Type 304, 321, 316) piping
system is not a new problem. This mode of failure can often result when
stagnant water s left inside the piping system for an extended period (i.e >
1 month). Consequently, this problem especially affects large projects with
long layup times between hydro testing / flushing / commissioning &
startup.
Typical features of this type of MIC
include:
• Pin
hole leaks, usually found in the bottom (between 5 – 7 "O" clock ) piping &
other locations where there is trapped
stagnant water (i.e. socket weld connections, non drain able expansion loop)
• The pits are often located at or
immediately adjacent to circumferential welds & are sometimes only found at
welds.
• The internal surface of the piping is
often covered with a reddish brown or slimy deposit.
• The pits have a typical ink- well
shape, such that they are often difficult to see & the full extent of sub –
surface damage is only revealed by probing the surface with a sharp object or
Radiography.
• Failure can occur in water with a
composition that cause corrosion of SS 300 series SS at ambient temperature
(i.e. as low as 100 ppm Cl-) & it must be noted that evaporation can lead
to concentration above the nominal level in the in put water. (Shell DEP
74.00.10.10-Gen states that “ Hydro test water shall not contain a
concentration of chlorides, either present originally or resulting from
evaporation, that may precipitate cracking or pitting”)
• The
rate of penetration is of the order of 1 mm/month, resulting in perforation of
standard schedule piping in 3 – 6 months from introduction of water to the
system.
Prevention –
Failure due to residual water from hydro testing can be
successfully avoided by diligent management of water quality & post – hydro
test draining & drying.
• Eliminate /minimize crevices in
fabrication.
• Avoid heat tint scale in pipe weld HAZ
with good inert gas purging. Where unavoidable, remove heat tint scale by
grinding / abrasive blasting / Pickling. Heat tint oxides make it poor barrier
to any corrosive media. In addition, the chromium depleted layer of base metal
beneath the heat tint is significantly less resistant to localized corrosion
then the base metal. The corrosion of the heat – tint oxide can also activate
the metal beneath it in a manner similar to free iron particles on a surface.
• Use non – wicking gaskets at flange
connections.
• All introduced water shall contain <
2 ppm chloride & be free from any suspended solids.
• Draining shall be done immediately.
Inadequate draining will lead to ineffective drying.
• System must be blown dry to ensure
complete removal of water at “hang up” points such as welds.
• Drying shall be done within 48 hours of
introducing water to the system. Use of specialized contractors with high
capacity dry air blowing units is recommended.
• The system shall be considered dry when
blown air at the system out lets has a measured dew point < 0 Deg.
Centigrade.
• Slope horizontal piping to make them
self draining.
• High
risk factors would include, but not limited to; long layup times, inadequate
drain points, high ambient temperatures, local contaminants (such as dust &
sand in a coastal environment), and limited availability of required quality
water. If any of these factors present, then advice should be sought from
Corrosion Engineer.
Good one, keep it up!
ReplyDeleteHello Guys,
ReplyDeleteI have a case study regarding pitting and pinholes in SS304 storage tank during service leak test which was hold for two days is this enough time to start MIC or pitting due to Chloride content. Please share your knowledge????